On October 7, Indiana utility regulators approved AES Indiana's arrangements for Google's planned 390-megawatt data-center load near Monrovia in Morgan County. October 12 reporting brings the decision into this review. The associated generation and storage project has an estimated $737.3 million cost; the load figure describes planned electricity demand, not an operating campus or the solar plant's capacity. Commission order, case 46394.
The approved structure includes minimum-demand payments, termination provisions and financial assurances. AES describes a minimum 15-year contract and an 80% minimum-demand obligation. The commission retains review of actual costs and their allocation in future rate proceedings. Nevertheless, WFYI reports testimony placing $32.3 million of direct-connection facilities on Google while $73.8 million of network upgrades enter the utility's regulated asset base for recovery through future rates. The order rejects requiring Google to pay every remaining network-asset dollar when its contract ends because those assets can continue serving others. AES's approximately $770 million customer-benefit estimate is a forecast, not realized savings. AES account.
Potential direction of power
Dispersion · Dispersion +1
Regulatory security and cost-allocation terms protect other customers if the large load scales back or leaves. They do not create public ownership; commercial redactions also limit outside scrutiny.
Window of contestability
Preserves
Preserves protection for other customers if the large load scales back or leaves; shared network costs still require public review.