Forest Grove, Oregon, adopted a 120-day data-center moratorium on October 12, with the city publishing its account October 13. The council voted 7–0 after a public hearing. The pause stops acceptance, processing and approval of new applications for data centers as a principal land use and for expansions of at least 20%. [The city's account](https://forestgrove-or.gov/m/newsflash/home/detail/191) confirms adoption and the principal-use and expansion scope.
Projects that already have land-use approval are exempt. That matters for an existing 2024 approval: the city has not cancelled all previously authorized development. The pause gives staff and residents time to examine electricity, land, housing and environmental effects and prepare code changes. It is temporary decision space, rather than a permanent ban or proof of successful cost protection.
Potential direction of power
Dispersion · Dispersion +1
Developers cannot obtain covered new approvals while local government develops its rules. That preserves public authority before projects create irreversible commitments.
Window of contestability
Opens
The temporary pause preserves a period for public rulemaking; permanent safeguards are not assured.