What happened
Governor Kathy Hochul issued Executive Order 62, directing the Department of Environmental Conservation to hold in abeyance incomplete applications for discretionary state permits, approvals, and licenses involving new or expanded data centers capable of consuming at least 50 megawatts. The pause remains in effect while the state prepares a Generic Environmental Impact Statement and develops standards addressing grid interconnection, environmental effects, water use, cost allocation, community benefits, and related infrastructure consequences. Projects whose relevant applications had already been deemed complete are not covered, local permits are unaffected, and primarily manufacturing, research, educational, and medical facilities are exempt.
Potential direction of power
Dispersion · Dispersion +2
Window of contestability
Preserves