DOE selects Brookfield and NextEra for Paducah AI-energy campus

What happened

DOE formally selected Brookfield to lease, develop, and operate an AI data-center campus on the federally owned former Paducah uranium-enrichment site and selected NextEra Energy to build and own its dedicated energy infrastructure.

Potential direction of power

Concentration · Concentration +2

The proposed privately financed development would exceed $100 billion, provide up to 1.8 GW of utility capacity and more than 1.2 GW of compute capacity, and add as much as 2 GW of natural-gas generation and 2.6 GW of battery storage. This converts federal land and inherited national-security infrastructure into the foundation for an extraordinarily large privately controlled compute-and-power complex.

The federal government is doing more than permitting private infrastructure. It is selecting the firms that will gain access to a strategic public site and using national AI leadership as the rationale for assembling compute, finance, generation, storage, transmission, and utility service at exceptional scale. Grid connection and Kentucky utility oversight preserve some public leverage, but the lease terms, customer allocation, public-interest obligations, community participation, environmental conditions, and enforcement of ratepayer protections remain largely undisclosed.