SUPPORTING EVIDENCE · OCTOBER ASSESSMENT
FERC accepts a large-load registry but rejects PJM’s proposed connection bargain
2026-10-09 · Dispersion +1 · October action
On October 9, the Federal Energy Regulatory Commission accepted part of PJM’s proposed tariff package: a definition of large loads and a registry describing major electricity users. It rejected the main Interim Resource Adequacy Service proposal, which would have allowed new large users to connect without matching new generating capacity if they accepted curtailment before grid emergencies. The registry provisions were accepted for October 12 effectiveness. The official docket entry ↗ identifies the partial acceptance and rejection in ER26-3515.
The proposed registry covers loads of at least 50 megawatts. Reporting describes location, demand growth schedules and capacity-supply information. FERC concluded that core service provisions intruded into state retail-rate authority and risked discrimination. This is not an order requiring data centers to bring their own generation or automatically lose power before households. A commissioner’s suggested household/hospital priority is a concurrence, not that operative rule. Final government access, confidentiality and implementation obligations still need examination in the order and accepted tariff.
The rejection is a completed October 9 institutional decision; no later final-rejection vote is needed. Pennsylvania PUC’s September 3 comments ↗ objected to retail compensation/jurisdiction and lack of state input. PJM disputed those objections in its September 23 answer ↗. Those submissions are party positions. Official decision metadata and independent reporting establish partial acceptance/rejection; the full operative order and accepted registry text remain inaccessible.
Supporting sources
- utilitydive.com · Source 1 ↗
- elibrary.ferc.gov · Source 2 ↗
- puc.pa.gov · Source 3 ↗
- pjm.com · Source 4 ↗
Open the existing event record →
This monthly evidence page preserves the underlying event and score. Implementation and source qualifications remain part of the assessment.