Case study
FERC subjects PJM Reliability Backstop Procurement to cost-allocation review
What happened
FERC/PJM accounts describe acceptance of Reliability Backstop Procurement suspended five months to February 28, 2027, with refund/proceeding conditions. Commissioner statements identify cost-causation and forecast concerns. The full operative order remained unavailable, and procurement did not begin September 30. This is distinct from the existing IRAS proposal.
Why it matters
Review can preserve a public opportunity to constrain costs shifted from new large loads to existing customers. Neither final protective tariffs nor operating generation are established.