Ohio's Supreme Court preserves Lordstown's ability to pause a data-center proposal
What happened
On October 20, Ohio's Supreme Court unanimously rejected a developer's attempt to force Lordstown to continue reviewing its proposed data-center complex under the rules that existed before the village's moratorium. Bristolville 25 Developer had started a preliminary site-plan process in October 2025, before the village imposed a ban and subsequently replaced it with a temporary pause.
The distinction matters: Bristolville had not completed the required preliminary stages or reached a qualifying zoning-permit application. The court therefore found no clear legal duty to continue its review under the earlier rules. This is a ruling about this project's procedural position, not a blanket finding that every application can be stopped retroactively. The actual opinion ↗ confirms the holding.
Why it matters
A municipality successfully defends its remaining development authority against a claim for compulsory processing. The holding is specific to the application stage, rather than a universal power to stop vested projects.