Watchlist · Finland: Muhos and Kajaani-Otanmäki

Finland confirms Google reported stopping site preparation—and demands a water-management plan

View the linked event assessment →

What happened

Finland’s Licensing and Supervision Authority published an October 22 follow-up concerning Google subsidiary Tuike Finland’s proposed data centers at Muhos and Kajaani-Otanmäki. This is older recovered evidence, not a new October 26 stop order. The authority’s October 6 instruction called for environmentally significant preparation to stop pending environmental assessment, immediately and no later than October 23. The follow-up says Tuike reported on October 14 that preparation had stopped at both sites.

The authority also requires a detailed Muhos water-management plan by November 5, including independent monitoring and provision for heavy rain, snowmelt and acidic runoff. Its signed document says Muhos drainage requires a water-law permit. Further compulsory enforcement remains a possible next step, rather than an already imposed fine. Necessary protective work must be distinguished from continued development. Agency follow-up and attached instrument ↗ provide more precise chronology than today’s English headline.

Why it matters

Public authorities are requiring assessment and water protection before further irreversible site preparation. The developer’s report of compliance is meaningful, but is not an independent inspection of conditions at the sites.

Supporting sources

  1. sttinfo.fi · Source 1 ↗
  2. sttinfo.fi · Source 2 ↗

Source snapshot: 2026-10-26. Individual event and verification dates remain as recorded above. Inclusion alone does not assign a score.