Supporting case
Taylor proposes a negotiated agreement for a privately powered computing campus
What happened
Taylor, Texas, published a proposed agreement October 2 for Big Watt Digital and PowerHouse's 664-acre computing campus near FM 112 and U.S. 79. The project includes on-site generation, but the official account does not establish its fuel or megawatt capacity.
Proposed conditions cover noise, setbacks, reclaimed water and developer-funded infrastructure. The cooling system would use closed-loop circulation, with potable-water exceptions including emergencies and reclaimed-service failures. The proposal lists $28.2 million for community, education and nonprofit benefits. Its $1.38 billion, 20-year tax estimate is a gross forecast, not a verified net public return.
This illustrates how a private-power campus still depends on public water, roads, permissions and fiscal arrangements. The bargaining outcome matters more than the headline benefit total: enforceability, payment timing and public costs determine the actual return.
Dates and implementation stage
Development: 2026-10-02