Supporting case
Uruguay and Solaria agree on a grid-connected data-center and solar development
What happened
Uruguay signed an agreement with Spain’s Solaria on October 14 for a proposed $5.7 billion development. Solaria’s October 15 stock-exchange filing describes up to 500 MW of data-center capacity, initially 200 MW and later another 300 MW, alongside 350 MW of solar generation. The programme is proposed development, not operating capacity.
Solaria would develop and operate a free-trade zone and its infrastructure, including connection to Uruguay’s 500-kilovolt transmission grid. The agreement provides for a power-purchase arrangement of up to 40 years with state utility UTE for the solar output. It does not describe a 500-MW data center running independently on 350 MW of solar. Data-center load, solar nameplate capacity and transmission voltage measure different things. Primary securities filing ↗.
Dates and implementation stage
Development: 2026-10-14