ERCOT recommends Amazon’s proposed Comanche Peak colocation; commission decision remains pending
What happened
ERCOT reportedly recommended an Amazon arrangement at the existing Comanche Peak nuclear plant in Somervell County on October 13. Proposed data-center load would grow from 100 MW in late 2027 to 1,200 MW in late 2031. These are proposed load stages, not operating capacity, and the recommendation is not Public Utility Commission approval. Explanatory reporting ↗.
The linked study and a consequential commission instrument remain uninspected. Reserving a substantial share of existing generation for a private campus could affect wider-system access. Binding emergency-curtailment, reliability and cost responsibilities will determine how much public control is retained. The reported Silver Basin approval is a separate proceeding.
Dates and implementation stage
Development: 2026-10-13; publication 2026-10-19