A remote Australian proposal combines a gigawatt-scale data center with its own energy system

What happened

Gingerah Energy's proposed Project Meridien, about 100 km south of Broome in Western Australia, entered federal environmental-referral publicity on October 21; reporting on October 22 and 26 was recovered today. The proposed campus would grow toward 1,000 MW of IT load, supported by up to 5.2 GW of solar, 1.5 GW of wind and 5 GWh of batteries, with gas firming. MW measures power; MWh measures stored energy. None of these figures is operating capacity.

Reporting identifies a joint venture involving the Karajarri Traditional Lands Association, Longreach Capital and Fugro, and an internal power network rather than an external-grid connection. The precise ownership shares, binding benefit/access rights, anchor tenant, financing and water requirements remain unverified. A federal referral asks whether further environmental assessment is required; it is not permission to construct. State and local approvals are separate. The public portal's indexed notice identifies referral 2026/10654, but its opened page did not expose the underlying records.

The distinctive mechanism combines a proposed computing campus, dedicated generation and land arrangements. Indigenous partnership could matter for retained authority and returns, but the reported partner names alone establish neither community control nor guaranteed benefits. Geographic dispersion alone is not dispersion of ownership or public power.

November 3, 2026 — evidence update

November 3 reporting adds important qualifications to existing case D1027-09, the proposed remote computing-and-energy campus south of Broome, Western Australia. Gingerah Energy and the Karajarri Traditional Lands Association told National Indigenous Times that Karajarri people have direct company participation, two directors and a project employee. They describe a 2024 community vote on a land-use agreement for renewable-energy development. That is not proof of a fresh community vote approving every current data-center component.

The partners say the reported up-to-1.5-gigalitre annual groundwater requirement is a maximum for construction over approximately ten years, rather than an established permanent cooling demand. A water licence would still be required. Gas suppliers and transport arrangements remain undecided. The newspaper reports a November 4 submissions deadline. The federal notice index ↗ confirms referral 2026/10654, published October 21; the complete underlying referral remains uninspected here.

This makes Indigenous participation more concrete while leaving ownership percentages, enforceable returns, veto rights and environmental obligations unresolved. The difference between construction water and operating demand materially changes the account, without resolving whether the project is environmentally acceptable.

Dates and implementation stage

Action/stage 2026-10-21; publication 2026-11-03