Glendale approves the Eagle/Baccara campus and its adjacent gas plant

What happened

Glendale’s elected City Council voted on October 27 to annex and rezone roughly 160 acres for the Eagle/Baccara development near Litchfield Road and Olive Avenue. Reporting identifies 6–1 votes on both Ordinance O26-38 (annexation) and O26-39 (project zoning), with Councilmember Leandro Baldenegro dissenting. These were elected council decisions, not administrative approvals.

The proposal combines three data-center buildings, an adjacent plant with 18 gas turbines and an APS substation. The applicant says EPCOR would supply water and wastewater service and claims lower water use than historic farming. Those statements do not establish executed supply arrangements or measured consumption. Ultimate ownership and anchor tenants remain unverified. City jobs/revenue and construction timing are forecasts.

Reporting describes 12 final zoning stipulations, including an agreement on specialized emergency and hazardous-material response before the first certificate of occupancy. The exact adopted terms, air permit, generation versus IT-load capacity and utility contracts remain to be inspected. This Arizona project is separate from Amazon’s Project Eagle in Wharton County, Texas.

Co-locating compute and generation increases campus control over energy while preserving dependence on public permissions and services. Elected approval establishes a consequential decision, but does not alone prove a dominant concentration or dispersion effect.

Dates and implementation stage

Development: 2026-10-27