PJM proposes enforceable ride-through duties for large customers
What happened
On November 16 PJM proposed that a new category of large customers at or above 50 MW remain connected during defined grid disturbances and meet compliance conditions. It cited about 3.9 GW of load that shifted unexpectedly on July 22. PJM proposed a January 16, 2027 effective date and roughly a year for existing facilities to comply; the requirements remain before FERC.
The political issue is who sets and can enforce the rules when a private operator's choices impose costs and disruption on others. A common requirement can give the regional grid institution more control over shared risks. It does not create a resident veto, set bill allocation, or by itself make PJM accountable to affected communities.
Dates and implementation stage
Action 2026-11-16; Publication 2026-11-16