Supporting case
Humboldt extends its data-center pause with a narrow renewable-power exception
What happened
Humboldt County adopted an extension of its data-center moratorium on November 17, 2026. The official docket records an ordinance as Passed with final action that day and describes an extension of ten months and fifteen days. An exact calendar end date is not asserted without the instrument.
The county's official staff account describes an exception for facilities below fifteen megawatts only when they use 100% on-site renewable electricity, closed-loop cooling and water that does not conflict with public-trust resources, and obtain a conditional-use permit. Being small alone does not qualify a project. The adopted extension is verified; inaccessible routine attachments do not hold the vote or these officially described terms.
The extension keeps public rulemaking time available while retaining a conditioned route for facilities below fifteen megawatts. It continues the same planning pause; permanent rules and any material change to exceptions remain separate decisions.
Dates and implementation stage
Action/evidence 2026-11-17; publication 2026-11-17