Indiana approves Google's Monrovia power agreement, with protections and shared network costs

What happened

On October 7, Indiana utility regulators approved AES Indiana's arrangements for Google's planned 390-megawatt data-center load near Monrovia in Morgan County. The associated generation and storage project has an estimated $737.3 million cost; the load figure describes planned electricity demand, not an operating campus or the solar plant's capacity. Commission order, case 46394 ↗.

The approved structure includes minimum-demand payments, termination provisions and financial assurances. AES describes a minimum 15-year contract and an 80% minimum-demand obligation. The commission retains review of actual costs and their allocation in future rate proceedings. Nevertheless, WFYI reports testimony placing $32.3 million of direct-connection facilities on Google while $73.8 million of network upgrades enter the utility's regulated asset base for recovery through future rates. The order rejects requiring Google to pay every remaining network-asset dollar when its contract ends because those assets can continue serving others. AES's approximately $770 million customer-benefit estimate is a forecast, not realized savings. AES account ↗.

The power mechanism is specific regulatory protection against a large customer scaling back or leaving, accompanied by continuing public review of cost allocation. Shared useful assets and net benefits require separate scrutiny. The arrangement does not establish public ownership of the assets. Public contract redactions also limit outside scrutiny, although regulators and parties had protected access.

Dates and implementation stage

October 7 IURC approval