The Race — Building Democracy in the Age of AI. People race toward a shared finish line.
The Race
← Trends

Supporting case

Townsite’s approval has reportedly been returned for further federal review

What happened

October 20 reporting, corroborated by an October 24 specialist account, describes an October 15 Interior Board of Land Appeals decision allowing further BLM review of Townsite Solar II near Boulder City, Nevada. BLM had authorized the data center using the environmental analysis for an earlier solar project. The new reporting describes the authorization as revoked and the project returned to BLM. The signed October 15 order remains uninspected.

On September 1, the Interior Board of Land Appeals had stayed BLM’s June 26 authorization for the proposed 167-megawatt project. The signed stay made public challenge effective before construction; it did not permanently cancel the project. The newly reported October 15 stage is a later lifecycle development, not a completed replacement environmental assessment or a permanent ban.

The dispute tests whether approval for a solar project can authorize a materially different computing facility without fresh public environmental review. The September stay made public challenge effective before construction; the reported later remand would reopen review, but its exact terms remain uninspected.

Dates and implementation stage

Underlying development 2026-10-15

Supporting sources

Related trends