TeraWulf doubles contracted Kentucky power at Muskie; delivery remains conditional

What happened

TeraWulf’s October 5 securities filing ↗ records agreements executed October 1 with Kentucky Power, an American Electric Power company. Its subsidiary’s contracted capacity at the Muskie campus in eastern Kentucky rises from 500 megawatts to one gigawatt. The company identifies the site as Grayson, Kentucky, in its filed investor presentation ↗, within EastPark Industrial Park. The first phase remains targeted to ramp in 2028; the second 500 megawatts moves from 2030 to 2029, subject to Kentucky Public Service Commission approval and the utility’s construction schedule.

These are grid-service and transmission-development agreements, not a one-gigawatt operating campus or an off-grid power system. An August investor presentation already described one gigawatt of contracted electricity. The October documents establish an amended agreement and the newly stated 2029 delivery target; they should not be treated as proof that the project first reached a one-gigawatt commitment in October. The company says development must comply with Kentucky’s data-center executive order. Neither the filing nor a capacity announcement establishes that ordinary customers are protected from every construction, stranded-asset or service cost. Water design and local-government service terms were not established in the available accounts.

For The Race, advance reservation of large amounts of electricity can shape who can scale. The existing Kentucky TeraWulf/Anthropic case concerns the separate 482-megawatt Justified campus and its regulated cost/curtailment bargain. Those protections must not be transferred to Muskie by analogy.

Dates and implementation stage

Amendment October 1, 2026; disclosed October 5; August 5 slides already describe 1 GW contracted electric service