Hayward adopts an initial 45-day pause, rather than a two-year ban

What happened

Hayward’s City Council unanimously adopted an immediate data-center moratorium on October 20. The city published its account October 21, and the Hayward Herald reported the meeting October 22. The official legislative history ↗ records passage, including a modification.

The initial period is 45 days. California law allows later extensions totaling up to two years; those extensions have not all been adopted. During the pause, the city can study cumulative resource demands, emergency-response needs and land-use consequences before approving new facilities. The existing Stack project under construction is not described as cancelled. The final modified ordinance is still needed for a complete account of exceptions and application handling.

The power mechanism is a temporary constraint on future permissions, giving public analysis a chance to precede additional commitments. A permanent prohibition or a new right over existing facilities would be a different action.

Dates and implementation stage

Action 2026-10-20; publication 2026-10-21