Coweta County returns Project Peach’s site to rural-conservation zoning

What happened

On October 20, 2026, Coweta County, Georgia, approved returning approximately 323.9 acres for Project Peach from Light Industrial to Rural Conservation. The county’s official recap confirms the reversal. On April 15, 2025, commissioners had granted North Coweta Investors LLC industrial zoning for a data-center operation, subject to 25 conditions. Condition 21 required a land-disturbance permit by October 16, 2026. Condition 23 required a will-serve letter and power purchase agreement; CyrusOne obtained a twelve-month extension of the original October 2025 power-agreement deadline.

The county’s September 28 staff memo said the required permanent power agreement and permit were still missing. Reporting on the October 20 meeting says temporary construction power had been arranged and site plans had entered initial review, but the required permit and permanent supply agreement remained outstanding. Commissioners voted 3–2 to return the land to Rural Conservation. Some preparatory work occurred; the failure concerns the required final conditions. The action removes the project’s industrial zoning entitlement, not an operating data center. The final instrument and any subsequent challenge remain follow-up evidence.

The elected county board made its conditions consequential by withdrawing an existing industrial development entitlement after the requirements were unmet. This returns the project to a public permission decision and is stronger than a temporary study pause. Its reach is project-specific; a future rezoning remains possible.

Dates and implementation stage

Action 2026-10-20; publication 2026-10-21