Supporting case
Cottle County signs a tax agreement with groundwater and road safeguards
What happened
On November 9, 2026, Cottle County, Texas, and RS 70 Land Holdings LLC signed a Chapter 312 tax-abatement agreement for Project Matter near Paducah. It took effect that day. It grants a 100% county tax abatement on eligible new improvements for ten years per phase. The signed reinvestment-zone resolution is a related action; the project remains proposed. Executed agreement and zone resolution ↗.
The owners owe ten annual payments in lieu of taxes per phase. At the first phase’s stated minimum, 180 MW at $3,884 per MW and 96 MW at $18,760 per MW produce $2,500,080 a year before credits. The owner owes a $1.5 million advance within 90 days; it may be credited in a later phase. The agreement specifies $1,957,000 in first-year community benefits for the county and eligible organizations on a county-approved schedule. Receipt has not been verified. The 180 MW is proposed dedicated gas generation; 96 MW is the proposed building figure, not verified IT load.
Article XIV bars operational groundwater use in Phase 1. For later phases, the owner must first implement or fund improvements and furnish county-approved engineering evidence that expected water benefits exceed project use. The county may not unreasonably withhold approval and can terminate subject to notice and cure. Article XVIII puts project-related road upgrades and extraordinary repairs on project owners and lets the county set standards, unless a separate road agreement supersedes those terms. Ordinary maintenance remains with the county.
The groundwater gate and road-cost obligations give the county project-specific approval and enforcement leverage now. Actual receipts, net fiscal return against ordinary taxation, public-service costs and compliance remain unverified. Statutory inspection and recapture alone would not explain the score.
Dates and implementation stage
2026-11-09: Scorecard Dispersion +1, lanes 9A/3/1, Leaning dispersion / Preserves
Supporting sources
Related trends
- The local data-center bargain is shifting toward an explicit public-return ledger
- Public ownership and recurring payments can make host benefits durable
- Compute developers assemble power and deployment control inside the campus
- Private infrastructure still relies on public water, services and permission