Supporting case
A ten-year anchor lease advances Project Clay in rural Hunt County
What happened
Giga Energy announced a roughly $1 billion ten-year lease with an unnamed US cloud provider on November 17. It plans to own and operate the 60 MW campus near Royse City, Texas. Construction started in July, with spring 2027 target service. Giga describes spare grid capacity on dedicated infrastructure and closed-loop cooling that avoids local demand for cooling. IT load versus facility demand, enforceable costs and net receipts remain unclear.
A private anchor lease can make the build viable. Lease revenue does not establish the public's return or who bears upgrade and service costs.
Dates and implementation stage
Action 2026-11-17; Publication 2026-11-17
