Mendocino extends its data-center pause, with a small-project exception
What happened
Mendocino supervisors voted 4–1 on October 6 to extend the September 1 data-center pause through August 21, 2028. Reporting describes an exception for facilities using less than 3 megawatts, healthcare exemptions and progress reports every four months. Adoption of permanent regulations can end the pause earlier.
The extension gives staff more time to develop rules before major projects obtain rights. Its long duration also reflects limited planning capacity; elapsed time alone does not demonstrate effective public bargaining.
The extension potentially preserves bargaining time before large projects establish facts on the ground. Its exemptions and the quality of eventual rules determine how much public leverage survives.
Dates and implementation stage
Development: 2026-10-06; Lifecycle history and future milestones in the description are separate