The Race

Policy tool · See record

Community participation in AI infrastructure decisions

What the tool does

Give residents a way to influence data-center siting and infrastructure rules through public meetings, submissions, hearings and appeals. Useful participation occurs early enough to affect location, resource demands, conditions or whether approval is granted.

Current status

In use through local planning and rule-design processes. Holding a meeting does not establish that residents can change a decision; access to evidence, review rights and the authority’s response determine the practical value.

Where it has been used

Colorado Springs’ Project Taurus appeal

Added by

Colorado Springs residents used the City Council appeal route to contest Project Taurus after administrative approval. The case shows how a local review process can give residents a formal opportunity to challenge an infrastructure decision; use of the appeal route alone does not establish that the permit was overturned.

Read more about this case →

San José’s initial standards consultation

Added by

San José invited public input in August 2026 before settling citywide standards for data centers and other large electricity users. Residents could address the standards before the city fixed its policy. The consultation was an input process, not adoption of a moratorium or final conditions.

Read more about this case →

Grande Prairie’s public-review procedure

Added on

A September 23, 2026 County of Grande Prairie account describes sending future data-center applications to the Municipal Planning Commission and neighboring residents for input. That prospective procedure does not reopen the earlier September 4 permitted-use approval. The formal referral instrument and exact adoption date are not established by the account.

Read more about this case →

Lee County’s late participation dispute

Added on

A proposed 180-day pause and additional hearing failed to gain support in Lee County on October 5, 2026. The existing Moncure permit was described as exempt. The episode illustrates the limits of participation after a developer has obtained a by-right permit; it does not establish that the existing approval was reopened.

Read more about this case →

Imperial County’s proposed voter consent

Added on

Imperial County repealed its June data-center moratorium on October 6 to comply with a court order. A replacement pause was a separate agenda item, so the repeal alone does not establish whether development is now unrestricted.

Supervisors also discussed a proposal to require voters to approve future data-center developments. That would shift the decisive consent from elected officials acting through the usual planning process to the electorate. The discussion did not adopt the requirement or place a measure on a ballot. A possible March 2028 election was discussed, not formally scheduled. Other environmental, land-use and water requirements would need to be reconciled with any final measure.

Read more about this case →

Denver’s data-center working group

Added on

Denver announced a 26-member data-center working group on October 7, 2026 after receiving roughly 250 applications. Members include residents, labor, academics, environmental representatives and industry participants. The group advises the city on rules during an existing planning moratorium. It cannot itself enact a zoning ordinance or approve projects.

Read more about this case →

Grande Prairie’s proposed zoning rules

Added on

On October 5, 2026, the County of Grande Prairie gave first reading to Bylaw 2680-26-046. The proposal would create zoning rules for new data centers and require a public hearing before covered approvals. First reading did not enact the permanent zoning changes.

Separately, the county describes an interim procedure sending new data-center applications to its Municipal Planning Commission, with neighboring owners able to provide input. The September 4 Emerson Trail permit remains issued, subject to its conditions and further approvals. The proposed rules do not establish cancellation of that permit.

Read more about this case →

New York’s community-investment guidance

Added on

New York’s September 15, 2026 Community Investment Framework recommends early resident input, transparent engagement, local investment priorities and defined implementation arrangements. Its suggested benchmark is $1 million per megawatt of utility demand, including required grid-modernization investments. This is recommended practice, not a universal mandatory payment or resident veto.

Read more about this case →

Townsite’s administrative appeal

Added on

On September 1, the Interior Board of Land Appeals, the Interior Department’s administrative appeals body, stayed the Bureau of Land Management’s June 26 authorization for Townsite Solar 2 LLC’s data center near Boulder City, Nevada. The signed order consolidated the city’s and environmental groups’ appeals and expedited consideration. The proposed project is described as 167 megawatts; it is not operating capacity.

BLM had relied on environmental analysis for a previously authorized solar-and-battery project instead of preparing a new or revised assessment for the computing facility. The panel found a persuasive likelihood that this treatment violated environmental-review requirements, and granted a stay after considering the four required factors. The ruling preserves the site while the appeal proceeds; it does not permanently cancel the project. BLM subsequently sought to set aside its approval and conduct additional review, according to September reporting. October 13 AP coverage still describes construction as stalled.

Read more about this case →

Mona residents’ permit appeal

Added on

On September 15, Mona Cares submitted an appeal asking Juab County, Utah, to overturn a conditional-use permit for a proposed campus just outside Mona. The project was approved in April and is described as roughly three million square feet. Residents say they did not understand that the earlier notices concerned a data center; county officials say they followed the law and provided notice.

The appeal also faces a timing dispute: the normal filing period is 30 days, while residents contend that minutes documenting the approval did not appear online until late August. October reporting describes continuing conflict and a September 21 commission meeting; it does not establish that the permit has been overturned. A resident’s account of a pipeline for a gas plant does not certify a final behind-the-meter design. Developer identity, approved power/water specifications and cost obligations remain to be established from the permit record.

Read more about this case →

Hood County’s permit-appeal decision

Added on

On October 13, Hood County, Texas, rejected Sailfish Investors' proposed Comanche Circle settlement 3–1 and unanimously denied its appeal of on-site permit decisions. The proposed development is near Tolar and the Hood–Somervell county boundary, close to Dinosaur Valley State Park. KERA's reporting describes hours of public testimony and dispute over county development rules.

The rejected compromise would have reduced the proposed footprint from about 2,523 to 1,375 acres and added conditions involving setbacks, cooling, lighting and roads. Those concessions never became an executed agreement. The developer's threatened litigation is not a filed lawsuit or a permanent project cancellation. Project electricity capacity, power supply and water arrangements remain insufficiently established for a complete rural-project profile.

Read more about this case →

San Antonio’s proposed approval rules

Added on

The proposed San Antonio hybrid would bring notice and public approval into siting. Actual participation rights and conditions require the final text.

Read more about this case →

Nye County’s adopted siting rules

Added on

Nye County, Nevada, adopted new regulations on October 8, reported October 14, with an October 28 effective date. They cover areas outside Hydrographic Basin 162, where the existing prohibition remains. Reporting describes a special-use permit requiring a public county hearing, a development agreement and studies of electricity, water, traffic, noise and public-service effects.

The reported final changes include a water-use cap and restrictions on evaporative cooling. A town board may provide a position, but its silence after 45 days does not veto the county application. The final ordinance needs comparison with the earlier draft and the pre-existing countywide pause; adoption is established more clearly than the exact final scope.

Read more about this case →

Newberry’s conditional approval rules

Added on

Newberry Township, Pennsylvania, adopted Ordinance 442 on October 13, according to October 14 reporting. Data centers would go through individual conditional-use approval in two industrial districts, allowing supervisors to assess whether a project meets the rules. The solicitor said no project application had yet been submitted.

The report describes water/noise studies, setbacks and security equal to 110% of estimated decommissioning costs before a building permit. That security would protect against an operator leaving closure costs behind; it is not a tax or a payment for operating impacts. The linked primary document is a review draft, so those detailed conditions need a final-text comparison. It is also necessary to establish whether the new ordinance restricts previously allowed development or enables a use previously not allowed.

Read more about this case →

San José’s draft data-center standards

Added on

San José held an October 15 public meeting on draft development standards; reporting published October 17 describes residents asking for stronger protection and a pause. The city has not adopted a moratorium or these standards. Its October 9 release describes requirements aimed at facilities using at least 20 megawatts, including carbon-neutral electricity, restrictions on potable-water cooling and backup-generator testing, and wider neighborhood notification.

The draft would also put consequential land-use and environmental appeals before the City Council. Proposed housing and energy-reliability charges remain under study; they are not current developer payment obligations. Planning Commission consideration is scheduled for November 18, followed by tentative December Council readings. The city says the eventual rules would cover applications still under review when the ordinance takes effect, making timing important for projects already moving through approval.

The new draft makes the possible bargain clearer, but neither a public meeting nor draft fees create another power shift. Resident demands also exceed what the city has committed to adopt.

Read more about this case →

Grove City voters give residents a binding decision before large industrial projects can proceed

Added on

Grove City voters approved a charter amendment that requires a public vote on covered large industrial projects after an independent study financed by the applicant.

Read more about this case →

Source snapshot: 2026-11-05. Individual event and verification dates remain as recorded above. Inclusion alone does not assign a score.