Temporary moratoria as rulemaking pauses

What the tool does

Temporarily prohibit new approvals while a government studies impacts and writes rules. A binding, time-limited pause can preserve public choices before projects secure development rights. Its scope, exceptions, duration and next steps must be clear.

Current status

In use through adopted local moratoria. Proposals for a pause are not operative restrictions. Loudoun’s earlier characterization as a binding pause was withdrawn; it is not counted here as an adopted example.

Where it has been used

Seattle’s planning moratorium

Added by

Seattle: the June 9 council account records adoption of an emergency moratorium and policy framework.

Read more about this case →

Centre Wellington’s one-year pause

Added by

Centre Wellington’s September 2026 council account confirms a one-year prohibition on data centers in specified zones. It creates a temporary planning pause rather than a permanent ban throughout the municipality. The final instrument’s complete exceptions are not established in the available account.

Read more about this case →

Vilas County’s proposed moratorium

Added on

local reporting describes a September23 committee recommendation for a twelve-month moratorium. Full-board action is expected November10; minutes/final scope remain held.

Read more about this case →

Lee County’s unsuccessful pause proposal

Added on

The reported 180-day pause and hearing failed to gain support; the existing Moncure permit was described as exempt. A late pause is not assumed to reopen vested development rights. Signed minutes/permit remain unverified. Meeting report.

Read more about this case →

Imperial County’s moratorium repeal

Added on

Imperial County repealed its June data-center moratorium on October 6 to comply with a court order. A replacement pause was a separate agenda item, so the repeal alone does not establish whether development is now unrestricted.

Supervisors also discussed a proposal to require voters to approve future data-center developments. That would shift the decisive consent from elected officials acting through the usual planning process to the electorate. The discussion did not adopt the requirement or place a measure on a ballot. A possible March 2028 election was discussed, not formally scheduled. Other environmental, land-use and water requirements would need to be reconciled with any final measure.

Read more about this case →

Mendocino’s extended planning pause

Added on

Mendocino supervisors voted 4–1 on October 6 to extend the September 1 data-center pause through August 21, 2028. Reporting describes an exception for facilities using less than 3 megawatts, healthcare exemptions and progress reports every four months. Adoption of permanent regulations can end the pause earlier.

The extension gives staff more time to develop rules before major projects obtain rights. Its long duration also reflects limited planning capacity; elapsed time alone does not demonstrate effective public bargaining.

Read more about this case →

Columbus County adopts a 120-day data-center approval pause

Added on

Columbus County, North Carolina, unanimously adopted its 120-day data-center moratorium on October 5. The official minutes now establish the vote and reproduce the ordinance. It suspends covered development approvals in unincorporated territory outside municipal planning jurisdictions while staff consult utilities and prepare standards. It can end earlier when new regulations are adopted. Existing permits, completed special-use applications and other protected development rights are exempt; ordinary accessory server rooms are excluded.

Read more about this case →

San Joaquin’s 45-day pause

Added on

San Joaquin County's board voted unanimously October 6 for a 45-day moratorium on land approvals for new data centers in unincorporated areas. The county announced the action October 7. The pause is intended to give officials time to develop an ordinance governing future projects, following an earlier direction to study their effects.

The relevant concerns include water and electricity demands and the conditions under which the county would approve projects. The action changes the approval timetable; it does not establish a permanent ban or demonstrate that a particular application has been rejected. The adopted measure's precise exemptions and effective period still determine its full reach.

Read more about this case →

San Francisco original pause completed executive approval; extension is separate

Added on

San Francisco's official record for ordinance 215-26 records mayoral approval on October 16, 2026. The planning department's November 10 assessment says the original data-center pause ends November 30. This resolves the outstanding question about executive completion of the original October 6 action.

The separate extension, file 261175, reached the Mayor's Office following the reported November 17 vote. No enactment date for that extension was established. The original signature therefore cannot be used as proof that the later extension is enacted.

Read more about this case →

Oakland’s urgency moratorium

Added on

Oakland’s City Council separately adopted an urgency data-center measure on October 6. File 27-0050 temporarily blocks new data-center land-use entitlements and related agreements while the city develops specific planning standards. The measure specifies immediate effect upon adoption. It is a temporary planning action, not a permanent ban or a finding that a particular application has been rejected.

Its purpose is to preserve a period in which local government can consider the water, electricity and land-use conditions attached to future developments. Exact project coverage, exemptions and extension provisions remain tied to the final ordinance.

Read more about this case →

Tulare’s extended pause

Added on

An October 1 state environmental filing reports Tulare County's extension of urgency ordinance 3669 for 10 months and 15 days, through August 6, 2027. It covers new data-center development in unincorporated areas while the county develops standards addressing land use, infrastructure, water, energy and public safety.

This is confirmation of the extension's reported scope and duration, not a new October 8 moratorium. The signed operative ordinance is still needed to settle the exact adoption date and exemptions.

Read more about this case →

Manatee County’s year-long pause

Added on

On October 8, Florida’s Manatee County commissioners adopted Ordinance 26-42 after its final public hearing. For up to twelve months, the county will stop accepting new data-center-related development applications in its unincorporated territory. The pause covers applications such as building permits, site plans, rezonings and development agreements. It can end earlier if the board repeals it.

The county’s existing land-development code does not specifically define data centers or large-load facilities. Staff will use the pause to recommend where these facilities belong and what rules should govern electricity and water demand, noise, setbacks, buffers and compatibility with neighboring properties. This is a planning pause, with an identified regulatory purpose, rather than a permanent prohibition. The county’s official account confirms adoption; earlier staff directions and planning-commission votes were preliminary steps. County account.

Read more about this case →

Raleigh’s pause and rulemaking timetable

Added on

Raleigh’s City Council voted 7–1 on October 6 for a six-month moratorium on major-data-center development applications. The city pauses acceptance and review while staff develops amendments to its Unified Development Ordinance, the rules governing local development.

Raleigh has published the next steps: a draft for public comment on November 16, planning-commission consideration in December and January, a council public hearing scheduled for March 2, and final action targeted for April 6, 2027, when the moratorium ends. The city says state law prevents an outright ban. Its existing special-use permit process also requires approval when an applicant satisfies the applicable standards, making the standards themselves especially consequential. City FAQ and timetable.

Read more about this case →

Humboldt extends its data-center pause with a narrow renewable-power exception

Added on

Humboldt County adopted an extension of its data-center moratorium on November 17, 2026. The official docket records an ordinance as Passed with final action that day and describes an extension of ten months and fifteen days. An exact calendar end date is not asserted without the instrument.

The county's official staff account describes an exception for facilities below fifteen megawatts only when they use 100% on-site renewable electricity, closed-loop cooling and water that does not conflict with public-trust resources, and obtain a conditional-use permit. Being small alone does not qualify a project. The adopted extension is verified; inaccessible routine attachments do not hold the vote or these officially described terms.

Read more about this case →

Anne Arundel’s planning pause

Added on

Anne Arundel County unanimously passed Bill 63-26 on October 5, 2026. The certified bill specifies November 26 commencement. Once effective, it pauses covered new applications until January 31, 2028 or earlier comprehensive legislation. Previously filed plans, associated later applications and future phases of existing centers on adjacent or adjoining land are excepted. A workgroup must examine resource use, siting, taxes, fees and other issues and report within ten months after commencement. The measure is therefore not a universal halt on all expansion.

Read more about this case →

Chatham County’s moratorium judgment

Added on

A North Carolina court ruled for Eco TIP West LLC in its challenge to Chatham County’s February 11, 2026 twelve-month data-center moratorium. Judge John Morris signed the judgment September 17 and it was filed September 18. The order grants judgment on liability and attorney’s fees while reserving damages. It does not identify a single decisive legal ground, so the result should not be read as invalidating every local moratorium.

Read more about this case →

Hill County’s rescinded pause

Added on

Hill County, Texas, unanimously rescinded its data-center moratorium on June 4, 2026 after RCM Hill sued for more than $100 million. The demand was not a damages award. The county substituted a development checklist covering infrastructure and community impacts. July 15 reporting describes a July 9 dismissal and a $100,000 legal-fee settlement. The checklist’s complete operative requirements and enforceability are not established by those reports. The case does not demonstrate that every Texas county moratorium is unlawful.

Read more about this case →

Silver City’s council adopts its data-center permit pause

Added on

Silver City’s council unanimously approved a resolution on October 27 temporarily suspending permits for data-center facilities within the town, according to Juno Ogle’s October 29 meeting report. The published council notice identifies Resolution 2026-29. Officials chose a resolution on advice from the town attorney and administration, with an ordinance possible later.

This advances our existing case from planning-commission recommendation to elected-council action. The earlier proposal contemplated a year for developing rules; the final resolution’s duration, exceptions and commencement still need checking. Silver City’s municipal action is separate from Grant County’s already scored moratorium.

Read more about this case →

Millington’s six-month pause

Added on

Millington, Tennessee, adopted Resolution 44-2026 on October 12, 2026, creating a six-month pause on new applications for specified off-grid generation, accessory computing and industrial-scale facilities. The measure gives the city time to assess utilities, public services, traffic, safety and neighborhood effects and prepare zoning changes. Projects approved at any stage and applications already formally submitted awaiting a hearing are excepted; the pause does not cancel every existing approval.

Read more about this case →

Shelby County’s proposed pause

Added on

On October 12, Shelby County, Tennessee, commissioners voted 5–4, with four abstentions, to advance a proposed data-center moratorium for unincorporated areas. WMC’s meeting report says another vote and a third reading remain before a final decision. This is a verified legislative step, not an adopted pause.

Commissioners Erika Sugarmon and Henri Brooks proposed creating rulemaking time before developers establish projects in those areas. Opponents questioned the county’s authority and the need for a pause when no projects were identified there. Memphis’s municipal proposal is a separate action; its next reported vote is October 20. The county proposal’s final duration, exemptions and commencement must come from its adopted text, if it passes.

Read more about this case →

Forest Grove’s 120-day pause

Added on

Forest Grove, Oregon, adopted a 120-day data-center moratorium on October 12, with the city publishing its account October 13. The council voted 7–0 after a public hearing. The pause stops acceptance, processing and approval of new applications for data centers as a principal land use and for expansions of at least 20%. The city's account confirms adoption and the principal-use and expansion scope.

Projects that already have land-use approval are exempt. That matters for an existing 2024 approval: the city has not cancelled all previously authorized development. The pause gives staff and residents time to examine electricity, land, housing and environmental effects and prepare code changes. It is temporary decision space, rather than a permanent ban or proof of successful cost protection.

Read more about this case →

Leon County’s 18-month pause

Added on

Leon County, Florida, unanimously adopted an 18-month pause on October 13. WCTV and the Tallahassee Democrat independently report the final vote. The measure covers large-load customer facilities, including large data centers, in the unincorporated county. It pauses acceptance, review and approval of covered development applications; it is not a permanent prohibition.

The county intends to study resource and community effects and develop comprehensive-plan and code amendments before processing future projects. The official September action record establishes that the earlier vote only advanced the ordinance to its final October hearing. Thus July's decision to prepare a pause and September's first hearing should not be mistaken for the operative adoption now reported.

Read more about this case →

Oregon’s environmental-permitting pause

Added on

Reporting published October 13 describes an October 9 letter from Governor Tina Kotek to environmental director Leah Feldon directing a pause on approval of new air and water pollution permits for new or expanded data-center projects until July 1, 2027. The mechanism is the Oregon Department of Environmental Quality's permitting authority, including federal programs it administers. It is narrower than a general prohibition on every construction activity or existing operation.

The letter ties the pause to recommendations from the state's Data Center Advisory Committee and possible reforms in the 2027 legislative session. The committee's preliminary report is accepting public comments until October 24 at 17:00. The article links the letter itself, but the accessible reporting does not settle every permit category, exception or implementation instruction.

The September 8 official direction covers state-owned property and access rights. Environmental permitting potentially reaches private-land projects. October 14 specialist reporting quotes a request to pause processing and issuance under DEQ’s existing discretion; the signed letter and agency implementation remain uninspected.

Read more about this case →

Lexington’s extended moratorium

Added on

Lexington-Fayette County approved ResolutionR-438-2026 on October 8, 2026, extending its data-center moratorium through October 31, 2027. The resolution covers zoning-map applications proposing data-center uses. Separate permanent zoning changes remained pending second reading on October 22. Reporting that specific size, power and noise limits were already settled conflicts with the official docket; those limits are not established as enacted law.

Read more about this case →

Perry Village’s limited moratorium

Added on

Perry Village, Ohio, adopted Ordinance 2026-13 on October 8, 2026, creating a one-year moratorium on acceptance and approval of data-center applications. The ordinance expressly excludes Champion Farm. It therefore does not stop the development at the center of the local controversy. The public notice establishes the duration and that exception; the full text is needed to establish every coverage detail.

Read more about this case →

Riverside’s proposed policy alternatives

Added on

Riverside, California's Land Use Committee directed staff on October 13 to bring two data-center policy options to the council on November 10. One would establish a 45-day urgency moratorium, potentially extendable to a total of two years. The other would formalize staff's interpretation that data centers are already prohibited because they are not listed as a permitted use.

The city planner said Riverside had received no data-center applications. This is therefore preparation before applications arrive, not rejection of a named project. A separate city AI working group is developing recommendations, and the committee wants to prevent approvals while that work proceeds. The identifies the session; the available local account reports the committee's direction, not full-council adoption.

Read more about this case →

Cleveland’s proposed extension

Added on

Reporting dated October 12 describes Cleveland council member Brian Kazy's plan to introduce an extension of the city's summer data-center moratorium by another 90 days. He cited three public meetings and tours of local facilities, distinguishing energy-intensive hyperscale development from smaller internet infrastructure. The report establishes the proposal and public process, not adoption of the extension.

The earlier pause was intended to allow City Hall to develop rules for new standalone data centers. Accounts give differing expiry dates, and the actual introduced extension and original operative ordinance still need comparison. No particular project is newly approved or permanently cancelled by the reported plan.

Read more about this case →

Johnson County’s moratorium extension

Added on

Johnson County, Iowa, supervisors unanimously extended the data-center moratorium in unincorporated areas on October 15, through August 8, 2027. The original pause began in November 2025. Reporting says the county wants more time to develop rules addressing siting, water, electricity and approval procedures.

Those possible permanent requirements are not already adopted because the pause was extended. The extension preserves an existing decision window rather than establishing a new one. Press-Citizen report.

Read more about this case →

Lordstown’s moratorium survives a developer challenge

Added on

Ohio’s Supreme Court ruled October 20 that the developer had not reached the qualifying application stage needed to compel continued review under earlier rules. The ruling preserves this municipality’s governing interval; it does not establish that every pending application can be stopped retroactively.

Read more about this case →

Brighton adopts a one-year rulemaking pause

Added on

Brighton completed adoption October 20 of a one-year data-center moratorium to develop code and procedures. The period runs from the effective date; the executed text, that date and final exceptions remain to be inspected.

Read more about this case →

Texas tests implementation of its permit pause

Added on

Texas’s governor directed the Texas Commission on Environmental Quality to halt covered data-center permits and required an October 19 compliance report. A September 21 extension continued the existing intervention. The directive does not itself enact a proposed elimination of tax incentives, and its application to individual permit files and projects outside ERCOT is not established.

October 20 reporting describes a dispute over continuing permit processing and TCEQ’s statement that covered stormwater permits had been suspended. The agency’s construction-permit notice expressly includes data-center projects. The actual compliance letter and individual suspension records remain to be inspected; preliminary processing and final permission are different stages.

Read more about this case →

Tango expansion follows an administrative approval route

Added on

Palm Beach County’s zoning director approved a revised Central Park Commerce plan on October 7, an action reported by WLRN on October 21. The site is in unincorporated western Palm Beach County near Twenty Mile Bend. The administrative approval adds about 64.46 acres to the development, bringing it to about 202.67 acres, and permits approximately 698,000 square feet of data-center use plus 54,000 square feet of accessory office space. The earlier plan allowed about 200,000 square feet of data-center use and 6,000 square feet of office space. The overall development retains its approximately 2.02-million-square-foot ceiling, including substantial warehouse space. The signed approval and development orders establish an entitlement, not an operating facility; other permits and existing development conditions still apply.

County commissioners rejected a separate, much larger expansion in July. The applicant nevertheless had an administrative route under its earlier approved plan. The county’s subsequent processing pause did not stop this pending application. That distinction matters: the October action does not establish that staff unlawfully reversed the commission, but it does establish a substantial expansion of private development rights without another commission vote on this application. The available approval does not establish operating IT capacity, final power architecture or water consumption.

Read more about this case →

Richmond pauses data-center approvals while writing rules

Added on

Richmond, California, adopted Urgency Ordinance 13-26 N.S. on September 15. The city’s official account establishes an immediate 45-day pause on issuing or approving permits and land-use entitlements for new data centers while it studies land use and develops rules. The initial period expires October 30. Its October 20 hearing notice proposed extending the pause by 22 months and 15 days. The notice covers facilities serving AI, high-performance computing, cloud services and cryptocurrency, while excluding subordinate server rooms serving another primary use.

An independent civic review of the October 20 meeting reports a unanimous extension through September 15, 2028. The final extension instrument has not been verified. The reported extension should therefore be distinguished from the original moratorium, which the city itself confirms was adopted. The original pause was enacted September 15.

Read more about this case →

Gilroy’s moratorium stops future applications while leaving the approved Amazon project in place

Added on

Gilroy, California, unanimously adopted an immediate 45-day moratorium on September 14. According to the city’s detailed explanation, it pauses future data-center applications while the city develops rules for siting and operation. It does not stop the previously approved Amazon Web Services facility already under construction. A second Amazon location had only reached preliminary discussions; a future formal application would be subject to the pause.

The city’s October 15 notice scheduled an October 19 decision on extending the moratorium by 10 months and 15 days, through September 3, 2027. October 21 reporting says the extension passed, but the final instrument has not been verified. The original September adoption is confirmed by the city and contemporaneous local reporting. An existing project’s exemption is a material boundary on the power effect, not evidence that the entire pause is ineffective.

Read more about this case →

Clackamas County adopts a pause on new and expanded data centers

Added on

On October 22, Clackamas County’s commissioners voted 5–0 to adopt a data-center moratorium. The county’s official draft minutes record the passed motion. The arrangement presented to commissioners suspends county approval of land-use and building permits for new or expanded primary-use data centers in unincorporated territory, while staff develops permanent rules. It does not govern incorporated cities merely because they are inside the county.

The staff-described initial pause lasts up to 120 days. A possible six-month extension requires another public hearing and findings about the continuing need and progress toward a solution. The signed resolution remains outstanding, so any final exceptions must stay qualified. The verified vote establishes adoption; the hearing calendar alone would not.

Read more about this case →

Grant County, New Mexico, approves a one-year data-center moratorium

Added on

Grant County commissioners voted 4–1 on October 22 to adopt a one-year pause on data centers and their directly supporting infrastructure. The Albuquerque Journal’s meeting report establishes the vote and quotes the restriction on establishing, constructing, developing, expanding or commencing covered facilities. The county’s identifies Ordinance O-26-03 and its application to unincorporated county territory.

The dispute includes the proposed Site Layer 1 project near Hachita. Commissioners want time to consider rules and resource effects. The developer and a landowner opposed the pause; one concern was whether its broad language could also obstruct environmental studies. The final ordinance is still needed to settle exceptions, commencement and that boundary. Neither the vote nor the project announcement establishes an operating campus or verified water demand.

Read more about this case →

Hayward adopts an initial 45-day pause, rather than a two-year ban

Added on

Hayward’s City Council unanimously adopted an immediate data-center moratorium on October 20. This is recovered news: the city published its account October 21, and the Hayward Herald reported the meeting October 22. The records passage, including a modification.

The initial period is 45 days. California law allows later extensions totaling up to two years; those extensions have not all been adopted. During the pause, the city can study cumulative resource demands, emergency-response needs and land-use consequences before approving new facilities. The existing Stack project under construction is not described as cancelled. The final modified ordinance is still needed for a complete account of exceptions and application handling.

Read more about this case →

Martin County adopts a one-year pause—but an existing application can proceed

Added on

Martin County, Florida, commissioners voted 4–0 on October 27 to pause new large-scale data-center applications for one year. The pause concerns unincorporated county land, where the county controls planning. Staff will use the interval to examine resource demands and possible comprehensive-plan and land-development-code changes. It does not govern the separate municipality of Indiantown.

The exception matters: a hyperscale proposal already filed near Kanner Highway west of Interstate 95 is unaffected. This is a pause on new applications, not a decision rejecting that individual project. Commissioners adopted the pause on second reading. The final ordinance's complete exceptions and commencement remain to be checked; reporting establishes adoption. County legislative record.

Read more about this case →

Jacksonville discusses a pause while deciding how to develop its own rules

Added on

Jacksonville, Illinois, council members discussed a data-center moratorium on October 26; reporting appeared October 27. Alderman Rob Thomas proposed six months, while Mayor Andy Ezard favoured a year. A resolution is expected November 9. The discussion concerns time for environmental, utility and fiscal study and public input, potentially with outside assistance. No pause was adopted at this meeting.

Read more about this case →

Iron County replaces its pause with permanent standards—but consultation remains contested

Added on

Iron County adopted permanent development rules and ended its temporary moratorium October26. The adopted final text and tribal consultation provision still require inspection. The county-linked draft’s30-day tribal input concerns qualifying individual developments; it is not a verified30-day ratification period for the ordinances.

Read more about this case →

Poweshiek County’s enacted planning pause

Added on

Poweshiek County, Iowa, voted 2–1 on September 28, 2026 to pause covered applications in unincorporated areas while it develops zoning rules. The signed resolution sets size thresholds, exemptions and deadlines. The pause preserves a public decision interval; the permanent standards are not yet decided.

Read more about this case →

Wiscasset voters reserve six months for data-center rules

Added on

Wiscasset voters backed a six-month pause on covered new and expanded data centers so the town can study local impacts and develop rules.

Read more about this case →

St. Johns County’s elected commissioners adopt a data-center pause

Added on

St. Johns County adopted a temporary pause on discretionary approvals for medium and large data centers on November 3. It took effect November 15. The exact exceptions and expiration terms remain a detailed-text check.

Read more about this case →

Oakland extends its existing data-center planning pause

Added on

Oakland extended its existing planning pause by ten months and 15 days on November 10. The original pause retains its earlier award.

Read more about this case →

Lawrence, Wisconsin, adopts a data-center pause while it writes rules

Added on

The Town of Lawrence Board of Supervisors voted 4–1 on November 9 to pause data-center review, approval and siting for at least one year while the town considers local standards.

Read more about this case →

Pitt County commissioners approve a two-year data-center moratorium

Added on

On November 16, Pitt County, North Carolina, commissioners voted to adopt a two-year data-center moratorium, according to two separate local newsrooms. The previously published county notice described pausing new applications while county officials examine zoning, utility capacity and local impacts. The notice confirms the contemplated scope but does not report the vote. The signed text, effective date, exemptions and treatment of pending applications have not been independently established.

Read more about this case →

Loudoun County pauses votes on discretionary data-center applications

Added on

On November 17 supervisors voted 7–1 with one abstention. They will delay final votes on covered data-center and electrical-substation rezonings and special exceptions while developing rules. The pause reportedly dates from September 15 and runs up to one year; administrative applications such as site plans can still proceed. Two independent reports establish the vote; exact effect and exceptions await the adopted text.

Read more about this case →

Salt Lake City adopts a 180-day data-center pause

Added on

On November 17 the council voted 6–0 to temporarily prohibit new data centers for up to 180 days while it develops rules for water and energy use, noise, lighting, air quality and related effects. The city ordinance is distinct from Salt Lake County's pause for unincorporated land. Northpoint may retain rights under a separate development agreement.

Read more about this case →

San Mateo adopts a forty-five-day data-center planning pause

Added on

San Mateo County supervisors adopted an immediate forty-five-day urgency moratorium on November 17, 2026, covering the siting, construction, conversion or operation of new or expanded data centers in unincorporated county territory. It reserves time to evaluate land-use rules, energy and water demands, environmental impacts and public-service capacity before additional projects proceed. It does not impose a ban inside incorporated cities or decide every future extension.

The official docket for file 26-932 now records the ordinance as Passed with final action November 17. Bay City News independently reports unanimous approval and immediate effect; its syndicated copies are one source family. The earlier October 20 direction concerned preparation of zoning changes, not this adopted pause.

Read more about this case →

San José pauses covered data-center approvals while preparing permanent standards

Added on

San José's City Council voted unanimously on November 17, 2026, to pause covered data-center and other large-energy land-use approvals until new standards take effect, according to San José Spotlight's first-hand meeting report. Twelve pending projects were affected. The official file 26-1220 matches the matter and scope but still shows a stale agenda-stage status, so it is not itself the evidence of adoption; syndicated copies of the local report are not independent confirmation.

The pause preserves the city's ability to set conditions before projects obtain approvals. Permanent development standards, including draft requirements about power, cooling, noise and public review, remain a separate decision.

Read more about this case →

McHenry County pauses new data centers for twelve months

Added on

McHenry County’s board approved a twelve-month moratorium on November 17, according to the November 20 first-hand meeting report. It stops the county from accepting, reviewing or approving covered data-center zoning and permit applications, including building permits, in unincorporated areas. Municipalities control their own territory. County planning director Adam Wallen said no data-center application was pending. Staff will use the interval to develop rules. The meeting report establishes passage but does not supply a numerical board tally.

Read more about this case →

Edenton adopted a temporary pause after postponing its proposed rules

Added on

Edenton’s council unanimously approved a temporary moratorium on certain data-center development approvals on November 10, with one member absent. Nicole Bowman-Layton’s November 11 meeting report identifies the vote and the purpose: examining effects on utilities, neighboring properties and public services. It reports a January 10, 2027 end date. The complete ordinance is still needed to settle its precise duration and exemptions.

Read more about this case →

Source snapshot: 2026-11-21. Individual event and verification dates remain as recorded above. Inclusion alone does not assign a score.